Sylke,
I am facing same issue.
How to display Project Analysis for Criticallity extractor in step 8.3. I've created a project in SOLAR01/SOLAR02 but it doesn"t display in CCM setup.I have already activated DVM & selected table utilization & data groth.
On same step I have created only project from SOLAR_PROJECT_ADMIN but I am not able to add business Scenarios
"
Start transaction SOLAR_PROJECT_ADMIN.
Create a new project.
On the System Landscape tab page, select a logical component for the project.
Save your entries.
Start transaction SOLAR02.
Select the project you just created.
In the Configuration Structure, under Business Scenarios, create a new scenario.
Create business processes.
On the Transactions tab page, add transactions to the business processes.
Create steps and add transactions to the steps.
Save your entries."
Thanks in advance.
Regards,
Amol